8. Appendix A
Table of permits and licences relevant to the storage development.
The table lists the different storage-related applications, consents, licences and permits01. The table is not exhaustive, but covers the major steps in the “permit-regime”. The laws and regulations governing the different permits are listed in Section 2.1. Note that the listed applications and permits could be processed/approved simultaneously or in slightly different order than listed.
Permit | Regulation/law | Regulation holder | Responsible authority | Status permits in Longship project |
---|---|---|---|---|
Survey licence | Storage Regulations, Chapter 2 | Storage operator | Ministry of Petroleum and Energy | Not applied in the Longship project |
Exploration licence | Storage Regulations, Chapter 3 | Storage operator | The King in Council | Not applied in the Longship project |
Permit to drill exploration wells | Regulations relating to materials and documentation in connection with surveys for and utilisation of subsea reservoirs on the continental shelf to store CO₂, Section 15 | Storage operator | Norwegian Petroleum Directorate | Drilling permit02 (boreløyve) (29.11.2019) |
Permit to drill investigation and injection well(s) | Pollution Control Act, Section 11 Management Regulations, Sections 25 and 26 CO2 Safety Regulations, Section 12 | Storage operator | Norwegian Environmental Agency, with consent from Petroleum Safety Authority | Drilling, Aurora field: Verification well (31/5-7, EOS): Permit, Norwegian Environmental Agency (25.09.2019) Consent from Petroleum Safety Authority03 (12.09.2019) Well 31/5-A-7 AH and 31/5-C-1 H: Application from NL04 (09.03.2022) |
Exploitation licence for underground reservoirs for injection and storage of CO2* | Storage Regulations, Chapter 4 | Storage operator | The King in Council (Ministry of Petroleum and Energy) | Exploitation licence, EL00105 (11.01.2019) |
Consent to establish a CO2 receiving facility | Regulations on the handling of flammable, reactive and pressurised substances and equipment used for this purpose, Section 17 | Storage operator | Norwegian Directorate for Civil Protection (based on Environmental Impact Assessment) | Consent from Norwegian Directorate for Civil Protection06 (15.04.2021) |
Permit for CO2 emissions | Greenhouse Gas Emission Trading Act, Section 5 (subject to the Pollution Control Act, Section 11) | Storage operator | Norwegian Environmental Agency | To be issued |
Permit to discharge (chemicals) when preparing the pipeline to the storage site | Pollution Control Act, Section 11 | Storage operator | Norwegian Environmental Agency | To be issued |
Permit for injection and storage of CO2 | Pollution Control Regulations, Section 35-4 Storage Regulations, Section 5-2 Management Regulations, Sections 25 and 26 CO2 Safety Regulations, Section 12 | Storage operator | Norwegian Environmental Agency (consent from Ministry of Petroleum and Energy, (Norwegian Petroleum Directorate), Ministry of Labour and Social Affairs, and Petroleum Safety Authority), ESA | Storage operator will apply closer to the start of injection (end of 2022 according to plan) |
Licence to install and operate facilities | Storage Regulations, Sections 4-5, 4-6, 6-1 and 6.2 CO2 Safety Regulations, Section 11 | Storage operator | Ministry of Petroleum and Energy, Petroleum Safety Authority | Plan to install and operate the transport, receiving- and storage facilities approved (PDO/PIO) by Ministry of Petroleum and Energy07 (25.02.2021) |
01 The English translations of the laws and regulations use both permit and license for the Norwegian term “tillatelse”. We have used the term that is used in the corresponding translation.
02 Boreløyve for brønn 31/5-7 i utnyttelsesløyve 001 – Oljedirektoratet (npd.no)
03 2019_1049-brv-equinor—samtykke-til-leteboring-av-co2-verifiseringsbronn.pdf (ptil.no)
04 Equinor søker om utslipp fra boring av CO2-injeksjonsbrønner på Aurora i Nordsjøen og fra legging av kontrollkabel. – Miljødirektoratet (miljodirektoratet.no)
05 Utnyttelsestillatelse-el-nr-1.pdf (npd.no)
06 Equinor får samtykke til mottaksanlegg for CO2 – Direktoratet for samfunnssikkerhet og beredskap (dsb.no)
07 Northern Lights – godkjennelse av plan for utbygging, anlegg og drift (regjeringen.no)
Gassnova is a state-owned enterprise under the Norwegian Ministry of Petroleum and Energy.
Gassnova is established to promote technological development, competence building and costeffective CCS solutions.